Permits must be pulled before work starts. Learn the timeline for each project type and avoid costly unpermitted work.
8–12 weeks before construction start. Early submission allows plan review time.
4–8 weeks before. Simpler scope means faster review.
12–16 weeks before. Complex projects need extended review.
2–4 weeks before. Straightforward scope.
4–6 weeks before. Weather-dependent work.
Finalize plans with architect/designer.
Submit complete application to building department.
Completeness check. Incomplete apps are rejected.
Technical review by officials.
Address requests for information.
Permit issued, work can begin.
Missing documents cause rejection and restart the clock.
5–10 day response window is tight. Plan accordingly.
Spring/summer can add 2–4 weeks to review timelines.
BAR approval adds 4–8 weeks.